Irrelevant. Boran is a niche product. It faced difficulties in the development phase but once it got military qualification (Land forces tested the shit out of that product) it is delivered and EXPORTED quickly. It was a difficult project for a company like MKE where every kg is important due to air-transportation and when you make it light recoil forces become a headache. There are not a lot of lightweight air-transportable howitzers around.
MKE has good production capacity. 35mm gun systems were never a bottleneck for the Korkut or air defense cannon project. TSK never had a problem for M60T or T-155 guns.
Once the 76mm naval gun system gets military qualification, MKE can produce them. MKE doesn't produce the servos, cooling system etc. Those might be a bottleneck. I don't know if producer companies has enough production capacity for outsourced systems.
Boran is not a niche product, it's a 105mm gun built to replace hundreds of 70 year old M101 and M116s in service. If anything, 76mm gun is the niche product that will maybe see 50-60 built during its production cycle discounting spare barrels, if we're lucky.
Boran was exported to Macedonia and Bangladesh, per claims by giving lines slated for KKK. Boran production is woefully slow. Per 2022 reports, Macedonia will get 6 Borans in 2 years and 12 more between 2029-2031.
"The first battery, each consisting of 6 BORAN Howitzers, is planned to be delivered to the Macedonian Army within 2 years, while the remaining 2 batteries are planned to be delivered to the Macedonian Army in 2029-2031."
Makedonya, Türkiye'ye 18 adet BORAN Obüsü siparişi verdi. Her birinde 6 adet obüs olan 3 batarya BORAN Obüsü, Makedonya Ordusu'na teslim edilecek.
www.savunmasanayist.com
In the original document signed in 2009, MKE was to deliver 104 Borans to army in 54 months or 4.5 years. That's 12 a year. We have more than 500 old mid caliber guns in service. Changing all of them(not currently planned or ordered) would take 20 years.
"For the 105mm Boran Howitzer Project, the Mechanical and Chemical Industry Corporation is developing the weapon system and Aselsan is developing the fire control system. According to the first contract, the contract period for the development of the howitzer was signed for 49 months, while the serial production phase of 106 105 mm howitzers was signed for 54 months."
Dağlık alanda ve arazide operasyonel birliklerin ihtiyacı olan yoğun ateş desteğinin düşmana görüntü vermeden sağlanması söz konusu olduğunda, akla ilk gelen düşük maliyetli silah sistemlerinin başında havadan taşınabilir hafif çekili obüsler gelmektedir. Soğuk savaşın sona ermesinden sonra...
www.defenceturk.net
Pretty normal to expect something similar for the 76mm gun and I will reserve my judgment whether MKE can deliver on time.