ambulance version of Gokbey is just offered by TAi so it might take some timeAzerbaijan will receive Hurjet in 3 years and Hurkush by the end of next year. Also, Azerbaijan will order ambulance version of Gokbey
Gokbey Ambulance with TS1400 should be no problem.Azerbaijan will receive Hurjet in 3 years and Hurkush by the end of next year. Also, Azerbaijan will order ambulance version of Gokbey
Can you really see any KAAN with US engines being sold to Azerbaijan?Because they are going to buy KAANs too?
That is one thing I really don't understand about the fervour to turn Hürjet into a light attack fighter or naval fighter. We don't even have an engine planned, let alone being actively work on like TF35K, for it, how on earth are we going to even use it ourselves, let alone exporting it?Hurjet is a worse scenario! We don’t even have an indigenous engine development that should fit in to Hürjet’s fuselage.
Azerbaijan will receive Hurjet in 3 years and Hurkush by the end of next year. Also, Azerbaijan will order ambulance version of Gokbey
Any sources confirming this?
This might be a completely idiotic question but I have to wonder; Can Hürkuş fulfill the role of a command plane? Directing a networked team of KE and Anka-III seems like a good use for it. I'm certainly not an expert on how that would happen, or would it even worth it. But I wonder.
i heard it from head of Tai when he was giving interview to Azerbaijani TV. ill try to find that..Any sources confirming this?
Depends on how it commands them though. It wouldn't have to be anywhere within hundreds of kms of the drones even with LOS communication as it would be in the air as well. But I still don't think it would be a good use for it.Too vulnerable.
www.defenceturk.net
What are the changes that Temel Kotil's timetables weren't realistic in the first place? I feel like this is now a change back to more realistic targets rather than a delay.Hürjet program update:
"Delivery of 4 Block-0 aircraft in 2027 and 12 Block-1 aircraft with the same configuration in 2028-2029"
Original announced calendar was 4 Block-0 aircraft for air force testing in by the end of 2025 and 12 Block-1s until end of 2028. 2 year delay, which will inevitably delay the type's acceptance by the air force.
![]()
HÜRJET teslimatında TUSAŞ'ın hedefi 2026
"2027 yılında 4 adet Blok-0 ve 2028-2029 yıllarında aynı konfigürasyona sahip 12 adet Blok-1 uçaklarının teslimatı öngörülmekte."www.defenceturk.net
Hürjet program update:
"Delivery of 4 Block-0 aircraft in 2027 and 12 Block-1 aircraft with the same configuration in 2028-2029"
Original announced calendar was 4 Block-0 aircraft for air force testing in by the end of 2025 and 12 Block-1s until end of 2028. 2 year delay, which will inevitably delay the type's acceptance by the air force.
![]()
HÜRJET teslimatında TUSAŞ'ın hedefi 2026
"2027 yılında 4 adet Blok-0 ve 2028-2029 yıllarında aynı konfigürasyona sahip 12 adet Blok-1 uçaklarının teslimatı öngörülmekte."www.defenceturk.net