LRIP in 2025 for Hürjet is very ambitious.
Comparable T-50 development from 2002:
2 static test ground units (20 months structural static/fatigue testing)
2 T-50 prototypes (trainer version 001, 002)
2 A-50 prototypes (LIFT version 003, 004)
- CDR passed in August 2000
- Assembly start prototype 15 January 2001
Assembly completed 15 September 2001
Roll out 1st prototype 31 October 2001
-
First flight 001 on 20 August 2002
- First flight 002 on 08 November 2002
- First flight 003 on 29 August 2003
- First flight 004 on 04 September 2003
First supersonic flight 18 February 2003 with Mach 1.05 at 40.000 feet (41st flight of 001).
1,411 test flights in total until certification.
- LRIP contract for first 25 T-50s signed on 19 December 2003
- First 2 T-50 delivered to ROKAF on 22. February 2005
They simultaneously tested the trainer and LIFT version but the timetable gives a hint what amount of work & flight hours is needed before starting with LRIP.
janes.migavia.com