If the TF-10000 is massively delayed, wouldnt that delay the TF-35000 as well?
As far as I remember, TEI planned to have the TF-35000 working by the end of 2028 and incorporate it into KAAN by the end of 2029/early 2030 for 2 years of testing following the official delivery by 2032
Not necessarily. TEI has a limited pool of engineers to run all those projects, and engineers are allocated to certain tasks from that pool. Let's assume you need 200 engineers to hit the timeline targets of TF-10000, but you can only allocate 20 engineers from the pool due to the ambitious timeline and needs of the TF-35000 project. This is what happened to the TF-6k/10k project. TEI redirected a lot of engineers to the TF-35000 project, which slowed down, especially TF-10000. TF-6000 was nearly done when engineers redirected to the TF-35000 project, but TF-6000 will also see delays because the work on iterative prototypes might slow down. Limited resources, overlapping priorities.
 

Sanchez

Experienced member
Moderator
Think Tank Analyst
DefenceHub Diplomat
Messages
4,093
Reactions
121 18,649
Nation of residence
Turkey
Nation of origin
Turkey
This timeline becomes plan A when the 110 engines fail to arrive.
Material realities don't care about plans. We saw the first instances of 2035 being iterated by reporters yesterday.
 

Oublious

Experienced member
The Netherlands Correspondent
Messages
2,768
Reactions
15 6,077
Nation of residence
Nethelands
Nation of origin
Turkey
Today is 9th, was ther a congres men crying about the sanction?
 

Angry Turk !!!

Contributor
Messages
703
Reactions
7 1,682
Nation of residence
Germany
Nation of origin
Turkey
That's why I said that Türkiye needs to buy more than 80. We simply do not know when TF35K will be ready for use.
 