It has already begun, they are conducting towing tank and cavitation tunnel experiment for propeller and hull design.This development will bring many other important news as well. Within 36 months, each of 3 shipyards will produce 1 I class frigate simultaneously and the cradle of military shipyard will be empty. This means that preparations for Tf2000 will begin... @Anmdt
View attachment 52963
Steel cutting is expected in May, July, September but could be a month earlier.Mr Demir:
"Within the scope of the project, each of Anadolu, Sedef and Sefine shipyards, is planned to construct an I-class frigate simultaneously.
The three ships are scheduled to be delivered in 36 months. TCG Istanbul, the first of the I-class frigates, has a local rate of %75. However, around 80 local subcontractors are involved in the project. The total number of companies working on the project is about 200."
The ceremonial steel cutting is scheduled for April 23 for all of the three hulls, but again, not guaranteed. Could be earlier.
This is why i have waited till 21st. He supposed to say these yesterday.