Translate in english please
*We have developed more than 34 of our own original engine design software.
*This first engine will integrate it into the TAI GÖKBEY helicopter.
*A budget of 80 million dollars has been allocated for the integration.
*Analyzes should be made and communication should be provided.
*These works take months or even a year.
*For example, one year after we delivered the PD170 engine, ANKA flew with this engine.
*We delivered the first engine so that integration work can begin as soon as possible.
*While TAI is being integrated, we will also produce new engines.
*The second engine will be ready for tests after 2 weeks and 5 engines will be produced in the summer of 2021.
*However, these will not be mass production engines.
*We will do tests such as sudden gas shut-off, sudden loading with these engines, which take a long time.
*We call these maturation and strain tests.
*We plan to squeeze everything into the next 3 years, get mass production certification and deliver the first ready-made engine in 2024.