TR TF-X KAAN Fighter Jet

Cabatli_TR

Experienced member
Staff member
Administrator
Messages
5,360
Reactions
81 45,455
Nation of residence
Turkey
Nation of origin
Turkey
Screenshot_20221027-103715_Word.jpg
 

Afif

Experienced member
Moderator
Bangladesh Correspondent
DefenceHub Diplomat
Bangladesh Moderator
Messages
4,797
Reactions
98 9,198
Nation of residence
Bangladesh
Nation of origin
Bangladesh
Congratulations to TUBITAK BILGEM!

I always thought this is the most difficult thing to develop for MMU after engine! But it seems they did it on the time.

But i always wondered why it wasn't given to ASELSAN! I thought, they had more experience in that area than anyone else in turkey. ( For example national mission computer of f16 )
 
Last edited:

MADDOG

Contributor
Türkiye Correspondent
Professional
Messages
1,220
Reactions
31 8,007
Nation of residence
Turkey
Nation of origin
Cyprus
"We are currently producing the landing gear detail components and subassemblies for the TF-X. We will be delivering them to our customers in November."

 

MADDOG

Contributor
Türkiye Correspondent
Professional
Messages
1,220
Reactions
31 8,007
Nation of residence
Turkey
Nation of origin
Cyprus
TF-X's assembly facilities. Plenty of activity visible. Could be someone important visiting, or just shuttles getting people from A to B. Satellite imagery seems relatively recent.

Screen Shot 2022-11-02 at 00.04.49.png
 

MADDOG

Contributor
Türkiye Correspondent
Professional
Messages
1,220
Reactions
31 8,007
Nation of residence
Turkey
Nation of origin
Cyprus
20221105_152020.jpg

(pic taken from me standing in front of the headquarters)




NOTE: Taking pictures inside the TF-X's assembly facilities is strictly prohibited. Taking pictures of Hürjet's assembly is also prohibited.


Locations visited:
-Hürjet
-F-16 structural and Özgür mod area
-MMU





HÜRJET
-Two prototypes are on the final assembly line. The number will increase to 4. There are two open slots for 2 more Hürjet fuselages.
-Piping and final assembly work in general takes A LOT of time and effort. The canopy and the tail section has gone on and off multiple times. It's all being handmade so this was expected.
-Hürjet will feature an Italian radar.
-Some crucial avionics have not arrived as of yet.
-Hürjet is set to feature a HMD.
-Hürjet's final assembly will be completed in a couple of months. Around the same time with the MMU.
-F-404's have been delivered and further deliveries are arriving as we speak. No delays or embargoes regarding the engines are expected.
-The aircraft stationed towards the right is the flying prototype, the one on the left will be used for static testing and it has its dedicated engine mock-up 🥺.
-No delays right now. Everything going according to plan. The assembly is also not going slowly, as per TAI officials.



F-16 Özgür
-There is a single Özgür prototype. It is not always stationed at TAI facilities.
-The Özgür program has gone serial! Which means the F-16's stationed there will undergo the Özgür modernization package.
-No major delays regarding the program as a whole. There is a small delay in place regarding the first aircraft waiting to be delivered. It must be noted that the Turkish Air Force is responsible for the inspection of the aircraft.
-First deliveries still expected in 2022.
-AESA integration planned in 2023.
-HMD will be developed.




MMU
-There is one aircraft being assembled. And that is the GTU-0. Like aforementioned, no RAM paint.
-Forward fuselage, mid fuselage, mid-aft fuselage (includes wing assemblies) are all completed. Aft fuselage is nearing completion.
-The canopy has been delivered.
-The forward fuselage will be transferred to the final assembly line in a VERY VERY VERY VERY short time. No pictures will be posted.
-Much of the crucial systems will be present during rollout. Certain systems such as the HMD, IRST, EOTS and other systems aren't expected to be there at first.
-TAI is using unorthodox techniques and technologies while assembling the aircraft. I'm not allowed to give insight on any of these.
-Even TAI technicians on sight were surprised to see how fast the program was moving forward. Assembly work is certainly moving at an incredibly fast pace.
-There are around 200 technicians on sight.
-The MMU hangar has transformed from an empty warehouse with a half-built FF, to a genuine assembly facility. This, I can proudly confirm.
-F-110's on sight. No delays expected for the rest of the deliveries.
-Certainly no delays to the program as things stand.





Other info obtained:
-Hürkuş will be delivered. TurAF simply has very high standards. The aircraft is not hampered by any critical issues.
-Hürkuş 2's CDR has been completed. I can confirm it will have a composite fuselage 😑
-The jet powered UAV... Not much to be seen unfortunately. They are certainly producing parts. And its assembly will be made at the dedicated UAV area.
-ATAK-2's assembly is going well. Most of the fuselage is not being made by TAI themselves. The company in question will deliver the fuselage and final assembly will start.


EDIT: Was set to visit MMU's simulator. But it's being managed by TurAF themselves and it was going through maintenance. So that didn't happen.
 

Glass🚬

Contributor
Messages
1,388
Reactions
2 3,159
Nation of residence
Germany
Nation of origin
Turkey
View attachment 50086
(pic taken from me standing in front of the headquarters)




NOTE: Taking pictures inside the TF-X's assembly facilities is strictly prohibited. Taking pictures of Hürjet's assembly is also prohibited.


Locations visited:
-Hürjet
-F-16 structural and Özgür mod area
-MMU





HÜRJET
-Two prototypes are on the final assembly line. The number will increase to 4. There are two open slots for 2 more Hürjet fuselages.
-Piping and final assembly work in general takes A LOT of time and effort. The canopy and the tail section has gone on and off multiple times. It's all being handmade so this was expected.
-Hürjet will feature an Italian radar.
-Some crucial avionics have not arrived as of yet.
-Hürjet is set to feature a HMD.
-Hürjet's final assembly will be completed in a couple of months. Around the same time with the MMU.
-F-404's have been delivered and further deliveries are arriving as we speak. No delays or embargoes regarding the engines are expected.
-The aircraft stationed towards the right is the flying prototype, the one on the left will be used for static testing and it has its dedicated engine mock-up 🥺.
-No delays right now. Everything going according to plan. The assembly is also not going slowly, as per TAI officials.



F-16 Özgür
-There is a single Özgür prototype. It is not always stationed at TAI facilities.
-The Özgür program has gone serial! Which means the F-16's stationed there will undergo the Özgür modernization package.
-No major delays regarding the program as a whole. There is a small delay in place regarding the first aircraft waiting to be delivered. It must be noted that the Turkish Air Force is responsible for the inspection of the aircraft.
-First deliveries still expected in 2022.
-AESA integration planned in 2023.
-HMD will be developed.




MMU
-There is one aircraft being assembled. And that is the GTU-0. Like aforementioned, no RAM paint.
-Forward fuselage, mid fuselage, mid-aft fuselage (includes wing assemblies) are all completed. Aft fuselage is nearing completion.
-The canopy has been delivered.
-The forward fuselage will be transferred to the final assembly line in a VERY VERY VERY VERY short time. No pictures will be posted.
-Much of the crucial systems will be present during rollout. Certain systems such as the HMD, IRST, EOTS and other systems aren't expected to be there at first.
-TAI is using unorthodox techniques and technologies while assembling the aircraft. I'm not allowed to give insight on any of these.
-Even TAI technicians on sight were surprised to see how fast the program was moving forward. Assembly work is certainly moving at an incredibly fast pace.
-There are around 200 technicians on sight.
-The MMU hangar has transformed from an empty warehouse with a half-built FF, to a genuine assembly facility. This, I can proudly confirm.
-F-110's on sight. No delays expected for the rest of the deliveries.
-Certainly no delays to the program as things stand.





Other info obtained:
-Hürkuş will be delivered. TurAF simply has very high standards. The aircraft is not hampered by any critical issues.
-Hürkuş 2's CDR has been completed. I can confirm it will have a composite fuselage 😑
-The jet powered UAV... Not much to be seen unfortunately. They are certainly producing parts. And its assembly will be made at the dedicated UAV area.
-ATAK-2's assembly is going well. Most of the fuselage is not being made by TAI themselves. The company in question will deliver the fuselage and final assembly will start.


EDIT: Was set to visit MMU's simulator. But it's being managed by TurAF themselves and it was going through maintenance. So that didn't happen.

will the tf-x rollout be in march or before that?
 

Follow us on social media

Top Bottom