Tusas CEO Dr Demiroglu has been giving out new dates and at the same time trying to divert attention from delayed Kaan P1 first flight with small news about other stuff. .
“KAAN is an aircraft in which all major systems—with the exception of just two—have been developed domestically. Its landing gear and actuators—the components that drive the movement of control surfaces—are domestically produced. Its oxygen system, radar, and munitions are also domestic; in short, it is truly a domestic product. We are also continuing our efforts to ensure that its engine becomes domestically produced in the coming years. KAAN is our most challenging and technologically advanced platform, boasting a level of domestic content that rivals even our land vehicles. Ground operations are currently underway for the first test prototype, designated “DAP-1.” Whether in October or November, we hope to see KAAN take to the skies this year.”
“We have one gasoline-powered, propeller-driven vertical take-off platform called ‘Gölge’; all our other platforms are jet-powered. We are working across three different categories: one platform with a range of up to 300 kilometers, another in the 600-kilometer range, and a third in the 1,000-kilometer range. All of them have successfully passed tests for aerial launching, catapult and ramp launching, and RATO (Rocket-Assisted Take-Off) launching. We have now entered mass production—not in the sense of traditional aviation mass production, but with production volumes closer to those of the automotive industry. Our goal is to establish a system where a platform rolls off the production line every hour or every two hours.”
Are we going to believe this?
He is the harbinger of deadline-delay . Not a single word he has uttered about Kaan P1 first flight has come true.
Second part, especially the last sentence is the biggest BS there is if you take Tusas’s past performance as norm. Seeing is believing. Put your money where your mouth is.
In Turkish:
Ayinesi iştir kişinin lafa bakılmaz
In his first detailed broadcast updates following his appointment, he stated that the P1 and P2 prototypes were expected to take flight by the
end of 2025.
later date Shifts: The expected first flight timeline for the P1 was later adjusted to
April or May 2026, then to
May or June 2026, and eventually pushed toward
late 2026 after it began ground taxi trials on July 31, 2026