Turkeys Indigenous Wind Turbine has a location for its Factory
> Finally after Years of Talks it will likely start producing in 2022/2023
View attachment 42052
View attachment 42053
View attachment 42054
I found the Location on a Satellite its east of Balikesir.
Date 30.03.2022
View attachment 42057
View attachment 42058
Partners of the MilRes Project
View attachment 42055
View attachment 42056
Here is the Entire PDF presentation with numbers from mid 2020.
I thought this was the only Wind Turbine Project in Turkey but that seem to be not the case.
There is at least one other Project.
1. Turbine Project MilRes
The Project was initiated in 2011.
The Factory is to be established and they haven't really started its construction yet, after 12 Years.
The Statement they put out 8 Months ago:
During the visit, the MILRES factory, which will be established in Balıkesir Dursunbey OSB, with an investment size of 165.000.000 TL, was discussed within the scope of the Ministry of Industry Investment Incentive. Within the scope of the meeting, the technical specifications and capacities of the turbines, which will be produced with 100% local technology and 100% locality, and the company's public offering process were evaluated.
> Locality Rate seems very ambitous.
2. YEKA-RES (Tender from 2017)
I was reading this article about Konya Karapinar Solar Farm
Kalyon Holding Yönetim Kurulu Başkanı Kalyoncu, Konya Karapınar'da hayata geçirdikleri güneş enerjisi santralinin (GES) aralıkta tamamının biteceğini belirterek, "Yıllık 2 milyon kişinin elektriğini karşılayacak." dedi. - Anadolu Ajansı
www.aa.com.tr
I noticed that Kalyon CEO mentioned YEKA RES-1
"Currently, we are producing solar energy panels in Turkey with 85 percent locality. We will do something new.
This will be a surprise. At the moment,
our goal is to produce wind turbines in Turkey. There is currently no production. Today, towers, blades and generators of wind turbines can be produced in Turkey. "We aim to produce wind turbines in our country with a
locality of more than 65 percent. We have an experienced and large staff and technical team involved in our work. We are working on this. It will be a huge gain for our country. We will be a company that exports high technology, not imports."
> Locality Rate seems lower than MilRes with approx. 65%
About the Tender and Winner:
The YEKA WPP competition organized by the Ministry of Energy and Natural Resources - General Directorate of Renewable Energy was won by
Kalyon-Türkerler-Siemens Consortium on 03.08.2017 with a price of 3.48 USD Cent/ kWh.
The YEKA Contract issued between Ministry of Energy and Natural Resources - General Directorate of Renewable Energy and Kalyon-Türkerler-Siemens Consortium has been signed on 26.02.2018.
The c
onsortium undertaken the factory installation that will manufacture turbines with a minimum 65% locality rate and it will carry out the R&D activities. Domestic employment will be provided in factory at the level of 90% and in R&D activities at the level of 80%.
YEKA RES Elektrik, kazandığı YEKA ihaleleri kapsamında, Edirne, Eskişehir, Kırklareli ve Sivas’ta toplam 1000 MW gücünde 6 adet Rüzgar Enerjisi Santrali (RES) kurup işletecek.
www.enerjigunlugu.net
> The Company created by the Consortium is
> The Deatails of the Tender
> 1000 MW Distribution of the Farms
"In his statement, Cemal Kalyoncu stated that the Karapınar YEKA GES-1 project, which is under construction, will be completed in December this year,
and that they plan to start the investment of the 1,000 MW YEKA RES-1 project in 2023."
> Kalyon in 2023 with their own Wind Turbine Factory Investment.
> The 2 Projects could have their Factories at a similar timeframe.
Also noteworthy in the same Year (2017) the same Group (Kalyon) won the tender for the Solar Panel Factory in Ankara.
20.03.2017
Karapınar Enerji İhtisas Endüstri Bölgesi'ndeki 1000 megavat (MW) kapasiteli Karapınar YEKA 1 GES İhalesini 6,99 dolar cent/kWh teklifiyle Kalyon Hanwha organ girişim grubu kazandı.
www.enerjigunlugu.net
03.08.2017
Enerji ve Tabii Kaynaklar Bakanlığının, bin megavatlık Rüzgar Enerjisi Yenilenebilir Enerji Kaynak Alanları (YEKA) ihalesi 8 konsorsiyumun katılımıyla...
www.hurriyet.com.tr
With KalyonPV they did a good job though, the Factory was supposed to have a capacity of 500MW and now they have 1250MW with more than 2100 Employees
In the production facility, starting from the raw material polysilicon, Billet (Ingot), Sliced Ingots (Wafer) and Cells and Panels are manufactured.
Kalyon PV Factory is one of the few projects in the world due to its locality rate, as it gathers 4 stages (Ingot, Wafer, Cell, Panel) under one roof.