Unless those choppers will also be used in civilian tasks(FYI they will be)Certificates are good things, but Turkey doesn't need an EASA certificate to deliver a Turkish helicopter to a Turkish government agency.
No ,TS-1400 tests are not finished yet,on the gökbey heli.Does this one have TS-1400 or nah?
Military certification would not be so long.First delivery Gokbey will be Gendarmery 30 August, total 26 will be deliverd to instutions and after that second contract talks with SSB.
They are talking 2027+ years later first TS1400 will be certified![]()
First delivery Gokbey will be Gendarmery 30 August, total 26 will be deliverd to instutions and after that second contract talks with SSB.
They are talking 2027+ years later first TS1400 will be certified![]()
So the total T70 deliveries as of august 24 is currently standing at 14, good info to have. First delivery was to JnGK back in december 22, so that's 14 helicopters in 19 months. Hope the license is extended by the Americans or this will be one let down and joke of a program.
-
And to add, if the license is not extended, get ready for an enlarged T625 or miniaturized T925, because a T70 sized helicopter is a literal necessity. And that's another 2-3 billion in the drain.
Certification programs EASA or not, take time. Also there may be some technical difficulties, these processes are perfectly normal. What is not normal is the created expectations about T625 entering services as soon as it flies.J-6001, first production T625 Gökbey for Gendarme is in Güvercinlik joint base, presumably for more trials and/or certification tests. J-6001 was rolled off in 2022 and is still not officially delivered to JnGK.
T625 first flew in 2018. We didn't create the expectations, they were claimed by the company GM at the time.Certification programs EASA or not, take time. Also there may be some technical difficulties, these processes are perfectly normal. What is not normal is the created expectations about T625 entering services as soon as it flies.
This aircraft was to be delivered to gendarme in Q1 2023, which was already a delayed date, because first 3 T625s were to be delivered to gendarme in 2022. Going even further, originally first delivery was to be made in Q4 2021, which was later updated to 1 T625 by H2 2022, which was later revised to first delivery in Q1 2023, then revised to Q4 2023, and we currently do not have any dates.
"The first batch of 3 helicopters is expected to be delivered in 2022. The delivery date for the T625 GÖKBEY was previously planned as October 29, 2021, which was later updated as 'mid-2022'."
Defence Turkey Magazine
www.defenceturkey.com
"Kotil announced that they will deliver the first GÖKBEY helicopter to the Gendarmerie General Command towards the end of 2022."
![]()
TUSAŞ 2022 yılında Jandarma'ya ilk Gökbey helikopterini teslim edecek
TUSAŞ, 2022 yılında Jandarma Genel Komutanlığı'na 3 adet GÖKBEY genel maksat helikopteri teslim edecekwww.defenceturk.net
Seems this was from last year when it visited there and not recent. Sad, we are passing another claimed delivery date, which was August 2024 for 2 T625s.J-6001, first production T625 Gökbey for Gendarme is in Güvercinlik joint base, presumably for more trials and/or certification tests. J-6001 was rolled off in 2022 and is still not officially delivered to JnGK.
![]()
I'm beginning to wish we had a different company focused solely on helicopters and related systems.Seems this was from last year when it visited there and not recent. Sad, we are passing another claimed delivery date, which was August 2024 for 2 T625s.