TR HÜRJET-Advanced Jet Trainer/ Light attack aircraft

Bogeyman 

Experienced member
Professional
Messages
9,192
Reactions
67 31,255
Website
twitter.com
Nation of residence
Turkey
Nation of origin
Turkey

HÜRJET is in production phase, assembly work continues

Prototypes will arrive by 2023

We anticipate it to enter the Air Force inventory in 2025.

We will use the General Electric F404 engine in HURJET

The same team is in charge of the Hürjet and MMU project.

The flight of the model that came out of the hangar will be made at the end of 2025 and the beginning of 2026.

First flight with GE F110 engine

When MMU enters the inventory, the domestic engine will be ready in 2029-2030.
 
Last edited:

Lool

Experienced member
DefenceHub Diplomat
Messages
2,921
Reactions
14 5,032
Nation of residence
Albania
Nation of origin
Albania

HÜRJET is in production phase, assembly work continues

Prototypes will arrive by 2023

We anticipate it to enter the Air Force inventory in 2025.

We will use the General Electric F404 engine in HURJET

The same team is in charge of the Hürjet and MMU project.

The flight of the model that came out of the hangar will be made at the end of 2025 and the beginning of 2026.

First flight with GE F110 engine

When MMU enters the inventory, the domestic engine will be ready in 2029-2030.
Wasnt the prototype of hurjet gonna be revealed in 2022 and first flight in 2023?
Pls dont tell me that they postponed it again?
 

Cabatli_TR

Experienced member
Staff member
Administrator
Messages
5,360
Reactions
81 45,455
Nation of residence
Turkey
Nation of origin
Turkey
TAI General Manager Assistant:

-Same team is in charge of Hürjet and MMU project
-We will make the flight of the model that came out of the hangar at the end of 2025 and the beginning of 2026.
-First flight with GE F110 engine
-When MMU enters the inventory, the domestic engine will be ready in 2029-2030
 

Lool

Experienced member
DefenceHub Diplomat
Messages
2,921
Reactions
14 5,032
Nation of residence
Albania
Nation of origin
Albania
The rollout was in 2022 but Kotil later said there will be no rollout. The Hurjet will likely be ready in 2022 but will not be unveiled at a ceremony.
So we wont get to see Hurjet in 2022?
 

Cabatli_TR

Experienced member
Staff member
Administrator
Messages
5,360
Reactions
81 45,455
Nation of residence
Turkey
Nation of origin
Turkey
Öztürk: Our project(Hürjet) is progressing very fast. We plan to complete this aircraft by the end of 2022. We will not make roll-out, we will make the first flight on March 18, 2023.

 

Combat-Master

Baklava Consumer
Moderator
Messages
3,667
Reactions
15 25,474
Nation of residence
United Kingdom
Nation of origin
Turkey
The rollout was in 2022 but Kotil later said there will be no rollout. The Hurjet will likely be ready in 2022 but will not be unveiled at a ceremony.

Ohwell, he did say early this year that it was going to fly in 2022 - early 2023 it is then (fingers crossed)
 

Lool

Experienced member
DefenceHub Diplomat
Messages
2,921
Reactions
14 5,032
Nation of residence
Albania
Nation of origin
Albania
Öztürk: Our project(Hürjet) is progressing very fast. We plan to complete this aircraft by the end of 2022. We will not make roll-out, we will make the first flight on March 18, 2023.

Damn, I do remember that they said the prototype will be ready in the early months of 2022.
Well minor setbacks are expected in such projects. I believe even the koreans suffered massive delays with their KF-X
 

Indos

Contributor
Think Tank Analyst
Messages
1,219
Reactions
1,537
Nation of residence
Indonesia
Nation of origin
Indonesia
Damn, I do remember that they said the prototype will be ready in the early months of 2022.
Well minor setbacks are expected in such projects. I believe even the koreans suffered massive delays with their KF-X

KFX/IFX started in 2011. There was delayed during 2013-2014 which is related to Korean side and more about financing and approval from their parliament. 2015 then the deal reached with Indonesia for the second phase of development. The timing is similar with the start of AMCA
 

Indos

Contributor
Think Tank Analyst
Messages
1,219
Reactions
1,537
Nation of residence
Indonesia
Nation of origin
Indonesia
I am very excited about hurjet. If only we could see the production of the prototype.

Hurjet is really a big achievement for TAI. T 50 Golden Eagle of Korea in the other hand gets significant LM contribution and assistance, particularly during design phase.
 

Cabatli_TR

Experienced member
Staff member
Administrator
Messages
5,360
Reactions
81 45,455
Nation of residence
Turkey
Nation of origin
Turkey
Öztürk: "Hürjet is slightly smaller than the F-16 but has many close features. Future versions will differ, of course. In particular, studies on material selection are ongoing."
 

Rodeo

Contributor
Moderator
DefenceHub Diplomat
Messages
1,330
Reactions
31 5,067
Nation of residence
Turkey
Nation of origin
Turkey
A question. How come Hurjet can do its first flight only a few months after its assembly while MMU requires 3 years of ground testing after its roll-out?
 

Siper>MMU

Contributor
Messages
542
Reactions
2 1,191
Nation of residence
Turkey
Nation of origin
Turkey
A question. How come Hurjet can do its first flight only a few months after its assembly while MMU requires 3 years of ground testing after its roll-out?
Hürjet design is freezed. Design engineers will focus on MMU while test etc ones will focus on Hürjet
 

TheInsider

Experienced member
Professional
Messages
4,066
Solutions
1
Reactions
34 14,482
Nation of residence
Turkey
Nation of origin
Turkey
A question. How come Hurjet can do its first flight only a few months after its assembly while MMU requires 3 years of ground testing after its roll-out?
Hürjet will be ground tested for close to a year.
 

Indos

Contributor
Think Tank Analyst
Messages
1,219
Reactions
1,537
Nation of residence
Indonesia
Nation of origin
Indonesia
A question. How come Hurjet can do its first flight only a few months after its assembly while MMU requires 3 years of ground testing after its roll-out?

Ground test usually takes about a year, even a simple plane like N 219 needs more than a year of ground test before making maiden flight.

About TFX it is Block 0 that is the real prototype that will undergone maiden flight, only about 1 year between prototype Block 0 roll out and maiden flight of TFX. You can look on the time table that has been posted in this thread.
 

Rodeo

Contributor
Moderator
DefenceHub Diplomat
Messages
1,330
Reactions
31 5,067
Nation of residence
Turkey
Nation of origin
Turkey
Hürjet will be ground tested for close to a year.
Then the date March 18th for the first flight no longer holds. It will be more like closer to the end of 2023. Maybe on October 29th?
 